Independent consultant
Gordon Belton (www.gordonbelton.com),
working for Halcrow Asia used Integer’s SuperSTRESS
software to design the stabling platform and maintenance facility
for the initial phase of the Bangkok MRTA project. The depot
was built under a design and construct project by a Thai-Japanese
consortium (lead contractor Kajima)
The depot was constructed 3m above an undeveloped
swamp area which had been de-watered and improved to permit access
for construction plant. The depot also crossed two major drainage
canals and had a plan area of 250,000 sq.m with a construction cost
of around US$ 150 million. The depot was completed as the
initial phase of the 20km subway project from Hua Lampong to Bang
Sue which was completed in 2004. |
|

Precast Concrete Slabs |
 |
The canal bridges were modelled in SuperSTRESS
as grillages and the slab structure modelled as a space frame, simulating
the slab with the supporting piles. Internal members were standard
rectangular sections, whilst the edge members were modelled with skew
edges to suit the on-site geometry. The structure was analysed
with two assumptions for the pile heads, being fixed or pinned to
ensure that the worst possible scenario of forces within the piles
and deck slab was designed for. |
The
piles were designed as hollow circular columns, under the effects
of prestress with vertical and lateral loads and movement under
traction loads with shrinkage, thermal and seismic effects.
Due to the relatively short span between piles, the effect of pile
differential settlement was not significant.
Design of the bridges and slab was to BS5400 but with
modified rail loads comprising fully loaded trains with individual
cars each having four 160 kN axles and with a 20 to 23m overall
length. A maximum train length of 120m was specified with
a track spacing of 3.73m. Other design loads for the structures
included self weight, ballasted track work, rail loading, highway
loading type HA plus 37.5 units of HB.
|
| The H-LOAD
software was used to simulate these train and highway loads crossing
the platform and bridges. Gordon said ‘The graphics
were particularly useful in checking and visualising the applied loads’.
Other loading applied to the structure included differential shrinkage
and thermal loading which was simulated using the distortion loading
type in SuperSTRESS. |
 |

H-LOAD
Graphics
|
|
Due to the small span
of member, together with the requirement to provide for freedom
of track/highway layout, the SuperSTRESS models were relatively
large (typically 3-4,000 members) and up to 60 loadcases were simulated
in the H-LOAD software. The Wood-Armer
calculation facility within SuperSTRESS was used very effectively
for analysing the skew slabs created by the triangular edge panels. |

Completed Platform
with Ballasted Track |
 |
The actual
construction of the deck of the canal bridges comprised precast
pre-tensioned M type beams. The stabling platform was constructed
of precast slabs supported on a 4 x 4m grid of 16,900 pre-cast concrete
spun piles 60 cm diameter and 30 m long. The modular precast
reinforced concrete slabs were supported on temporary clamps at
the pile head and an in-situ concrete upper slab was poured to form
a composite deck slab which minimised the need for formwork and
support from the soft ground below.
|